The firm continues its infrastructure, feasibility study and staffing efforts for its Idaho Cobalt Project.

Idaho Cobalt Project construction

eCobalt Solutions Inc. (ECS:TSX; ECSIF:OTCQX; ECO:FSE) provided an update on its Idaho Cobalt Project, specifying development tasks that have been recently completed and tasks that remain in progress. "I am very impressed with not only the volume of work but also the quality of work that has been done on the ground by the team," said Michael Callahan, president and CEO.

As for what has been done, the maintenance building is up and working. Potable water and power systems are installed and functioning. The water management ponds are finished. The wildlife fence is up. The pumpback system has been electrified. Water treatment pipelines are installed and winterized.

Regarding what is yet to be completed, the liner of the tailings waste storage facility is one; it is 33% done. That project will be covered for the winter and finished in the spring. The finished portion now can accept waste rock. Mill foundations are nearly halfway done (40%). Construction of phase 1 of the portal bench, underway, should be done in 2018.

With respect to the water treatment plant, it remains under construction inside the finished water treatment plant facility. The mechanical component is slated to be completed by the end of November. Next year, commissioning of the plant and pumpback system will occur in preparation for launching underground operations.

As for progress of the new feasibility study for the Idaho Cobalt Project, Callahan noted that the company "is in the final stretches of finalizing" it.

In other news, eCobalt hired Mark Kockler to be the mine manager of the Idaho Cobalt Project. With more than 23 years of industry experience, Kockler most recently worked as the operations liaison manager and technical services superintendent at Goldcorp's Cerro Negro. His resumé also includes positions at Barrick Gold Corp., Newmont Mining Corp., Mines Management Inc., Idaho General Mines Inc. and Placer Dome Inc., among others.

[NLINSERT]

Disclosure:
1) Doresa Banning compiled this article for Streetwise Reports LLC and provides services to Streetwise reports as an independent contractor. She or members of her household own securities of the following companies mentioned in the article: None. She or members of her household are paid by the following companies mentioned in this article: None.
2) The following companies mentioned in this article are billboard sponsors of Streetwise Reports: eCobalt Solutions. Click here for important disclosures about sponsor fees.
3) Comments and opinions expressed are those of the specific experts and not of Streetwise Reports or its officers. The information provided above is for informational purposes only and is not a recommendation to buy or sell any security.
4) The article does not constitute investment advice. Each reader is encouraged to consult with his or her individual financial professional and any action a reader takes as a result of information presented here is his or her own responsibility. By opening this page, each reader accepts and agrees to Streetwise Reports' terms of use and full legal disclaimer. This article is not a solicitation for investment. Streetwise Reports does not render general or specific investment advice and the information on Streetwise Reports should not be considered a recommendation to buy or sell any security. Streetwise Reports does not endorse or recommend the business, products, services or securities of any company mentioned on Streetwise Reports.
5) From time to time, Streetwise Reports LLC and its directors, officers, employees or members of their families, as well as persons interviewed for articles and interviews on the site, may have a long or short position in securities mentioned. Directors, officers, employees or members of their immediate families are prohibited from making purchases and/or sales of those securities in the open market or otherwise from the time of the interview or the decision to write an article, until one week after the publication of the interview or article.





Want to read more about Cobalt / Lithium / Manganese investment ideas?
Get Our Streetwise Reports Newsletter Free and be the first to know!

A valid email address is required to subscribe